Short answer. Software that is useful to a construction company in Algeria in 2027 holds five things. Pricing: items of work broken down into materials, labour and equipment, a measurement, a written coefficient. A budget per site, taken from the signed quotation, trade by trade. Execution booked to the site: purchases, deliveries, timekeeping, equipment, subcontractors, entered on the spot. Progress claims calculated from the quantities done, and followed until payment. Steering: progress against spending, projected margin, cash. The yardstick that decides: if a site has spent 45 % of its budget for 40 % of the work done, its margin is already eaten into, and that shows in week nine, not week twenty.
This guide is for the building or public-works contractor running several sites at once, structural work, finishing trades or roads, for the site manager who keeps sites in spreadsheets, and for the founder based in France who finances or runs a works company in Algeria without seeing the sites. The notions quoted are those of public references: the bill of quantities, earned value, retention; cost overruns are described there as common in building and infrastructure projects. The numbers in the figures are a constructed example. This guide gives neither market prices nor legal rules: contract clauses, public procurement rules, retentions and payroll are matters for your legal adviser and your accountant.
One site, week 9: 40 % done, 45.6 % spent
The figure follows a twenty-week site with three curves: what was planned, what is done, what is spent.
Three figures. The site has a cost budget of 9.0 million dinars for a contract of 10.2 million: 1.2 million of planned margin. At week nine, the schedule planned 3.83 million of work. The work actually done, valued at budget prices, is worth 3.60 million: 40 % of the site. Spending, though, has reached 4.10 million: 45.6 % of the budget. This is the method references call earned value: comparing the value of the work planned, the value of the work accomplished and the actual cost.
What follows. For every dinar spent, the site produces 0.878 dinar of work, 3.60 divided by 4.10. If it carries on like this, it will cost 9.0 divided by 0.878, that is 10.25 million: about the contract price. The 1.2 million margin has gone, and nobody knows, because supplier invoices are in a binder and hours in a notebook. What changes. At week nine, eleven weeks are left to act: renegotiate a supply, correct an output, bill additional work that was never priced. At the final account, none are left. That takes two things a spreadsheet does not hold: a budget per trade, and spending booked to the site on the day it is incurred.
«At week nine, eleven weeks are left to correct. At the final account, none are.»
Six real situations, and what the software must do
Each row is something a contractor says, and the answer is a way of running the site, not one more module.
I find the loss at the end of the site: that is the previous figure; without a budget, spending is compared with nothing. My quotations are made from memory: a price per square metre copied from the previous site does not say what it contains; the next figure breaks it down. Cement is ordered three times: each site manager phones the supplier; a request leaves the site, becomes an order, is received on site, and the quantity is compared with the budget, following the chain described in the guide to sales management software.
Progress claims go out late: quantities are noted on paper, then recalculated at the office; entered on site, they give the claim the same day. I do not know who was on which site: timekeeping is done per site and per trade, from the foreman's phone or a time clock, as in the guide to time clocks and timesheets; hours are valued in the site's cost, payroll remaining a matter for your accountant. The client disputes what was done: a site diary, dated photos and quantities approved by both parties are worth more than an argument six months later.
The price of one item of work: from 1,850 to 2,553 dinars per square metre
The figure breaks down the price of one square metre of wall, then shows what happens when the output falls.
The breakdown. A construction quotation is a list of items of work, each with a quantity and a unit price; references speak of a bill of quantities, in which materials, parts and labour are itemised with their costs. For one square metre of wall, the example counts 1,150 dinars of materials, 620 of labour and 80 of equipment: 1,850 dinars of direct cost, what the item consumes directly. Site costs, 222, overheads, 185, and the margin, 296, are added: 2,553 dinars, a coefficient of 1.38 applied to the direct cost.
The hidden assumption. The 620 dinars of labour assume that a mason lays eight square metres a day. If he lays six, labour goes to 827 dinars and the margin falls from 296 to 89: seventy per cent less margin for two square metres fewer. Over the 640 square metres of the quotation, the planned margin of 189,440 dinars becomes 56,960. What to take from it. A price that is broken down says which assumption to watch on site: here the output, elsewhere material waste or the price of steel. A library of items broken down, updated with the outputs observed on your sites, is what makes the next quotation more accurate than the last. The pricing engine itself is described in the guide from quotation to invoice.
«Two square metres fewer per mason per day, and seventy per cent of the item's margin disappears.»
A progress claim, in six steps
The third step is accented: the running total is what avoids billing twice, or forgetting.
Record the quantities done, item by item, on site, with the client's representative when possible. Value those quantities at the prices of the signed contract, not those of the original quotation if they have changed. Accumulate: a claim covers everything done since the start; the previous claims are deducted to obtain the month's amount.
Withhold what the contract provides: references describe retention as a portion of the price deliberately withheld until the work is complete; its terms, like those of advances, are those of your contract and are checked with your legal adviser. Get approval from the client or their representative, and keep the record. Collect: the invoice, its due date, the reminder, as in the guide to customer credit. Software that produces the claim on the day of the record shortens the time between work done and money received; it is often cash, more than margin, that puts a construction company in difficulty.
Construction software, in five layers
The accented layer is the site budget: it is the reference everything else is compared with.
Pricing. A library of items broken down, a measurement, a coefficient. Site budget. The signed quotation becomes a budget: by trade, quantities, hours, materials, subcontracting. It is a transformation, not a retyping. Execution. Everything that is spent carries the name of a site and a trade: the cement order, the delivery received, the crew's hours, the hire of a concrete mixer, a subcontractor's invoice. Entry is done on the spot, on a phone, including where there is no network, as in the guide to offline use.
Claims. The quantities done feed both the progress claim and the site's progress: one entry, two uses. Steering. Per site and per trade: progress against spending, projected margin, and cash for the coming weeks, expected receipts against purchases and wages, on a board like the one in the guide to the manager's dashboard. And accounting. Site software does not replace it: it passes on invoices and receipts, as in the guide to integration.
Construction software in 2027, in weeks
Five weeks in the example, the first with nothing installed.
- What the manager sees: for each site, progress, spending, projected margin, pending claims and cash for the coming weeks, from their phone.
- What the company no longer does: discover the loss at the final account, order the same cement three times, recalculate a claim at the office, price from memory.
- What is measured: progress against spending by trade, observed output against planned output, time between work done and claim issued, collection time.
- What Symloop does: build the library of items with you, rebuild the budgets of sites in progress, set up purchases, timekeeping and claims on the phone, link accounting, and deliver the manager's board, with an off-the-shelf tool configured or an application built for you.
Week 1, items and sites: the thirty or forty items that keep coming back in your quotations, broken down with the site manager, and the list of sites in progress. Week 2, budgets: each open site gets its budget by trade, rebuilt from the signed quotation, and its progress to date; that is when you learn, for each one, whether it is making or losing money.
Week 3, purchases and timekeeping: requests, orders and receipts per site, timekeeping by trade on the phone, on two pilot sites. Week 4, claims: the first progress claim produced by the software, collections followed. Week 5, manager's board: progress against spending, projected margin, cash for the next eight weeks. Off the shelf or custom. Quotation and site-tracking software exists, and suits you when your sites resemble one another; custom development is justified when the company has its own ways of pricing, several lines of work, or sites to follow from abroad. In both cases, the library of items and the budgets belong to you and must be exportable.
- What is site management software?
- It is the software that links a site's quotation to what happens on it: it turns the signed quotation into a budget by trade, books purchases, hours, equipment and subcontracting to that budget, calculates progress claims from the quantities done, and shows progress, spending and projected margin at any time.
- Which software should a construction company in Algeria choose?
- The one that holds your items broken down, a budget per site and per trade, entry on the phone from the site, your progress claims as your contracts require them, and the export of your data. Try it with a site in progress: if it tells you within an hour how much that site has spent and what it has left, it does the job.
- How much does construction software cost?
- A licence or a subscription per user for an off-the-shelf tool, plus the library of items, the take-over of sites in progress and training; custom development is priced on its scope. This guide gives no price. The useful yardstick is what a single site loses when the drift only shows at the end: in the example, 1.2 million dinars of margin.
- Is quotation software enough?
- No. A quotation says what the site should cost; it does not say what it is costing. Without a budget taken from the quotation and spending booked to the site, the quotation remains a sales document, and the margin is discovered at the final account.
- How can I tell whether a site is making or losing money before the end?
- By comparing two percentages: the share of the work done, valued at budget prices, and the share of the budget spent. If spending is ahead of progress, the site is drifting; the ratio between the two gives the likely final cost. In the example, 40 % done for 45.6 % spent points to a final cost of 10.25 million for a budget of 9.0.
- How do you follow several sites at once?
- By giving each its budget, and by requiring every purchase, hour and hire to carry the name of a site. The manager then reads a board with one line per site: progress, spending, projected margin, pending claims. The sites that are drifting rise to the top of the list.
- Can the site manager enter data from a phone, with no network?
- Yes, if the application is designed for it: it stores quantities, timekeeping, receipts and photos on the phone, then sends them when the network returns. It is a condition to check before choosing, because the information is born on site, not at the office.
- How is the price of an item of work calculated?
- Add up what it consumes directly, materials, labour and equipment: that is the direct cost. Multiply it by a coefficient that covers site costs, overheads and margin. In the example, 1,850 dinars of direct cost and a coefficient of 1.38 give 2,553 dinars per square metre. The amounts are those of the example.
- Does the software handle public contracts?
- It calculates the documents a contract requires, bill of quantities, progress claims, final accounts, from quantities and prices. The rules specific to public procurement, its documents and deadlines, are not covered in this guide: they are checked with your legal adviser, and the software is then set to what is required.
- I run the company from France: what can I see?
- The board of sites, with progress, spending and projected margin; the dated photos and the diary of each site; claims issued and collected; cash for the coming weeks. Enough to ask the site manager the right questions without waiting for month end.